Long Thanh Airport is scheduled to open on December 24, starting with around 30 flights per day

Some links on this page contain advertisements.
Ground staff inspecting baggage vehicles at Long Thanh International Airport as it prepares to open.

Long Thanh International Airport in Dong Nai Province is scheduled to begin commercial operations on December 24, 2026. According to the contents of a working meeting reported by VnExpress, the initial phase will see approximately 30 flights per day, of which 4 routes will be international. The maximum number of flights per week is projected at 366 (322 domestic, 44 international), with Vietnam Airlines and VietJet Air as the carriers. The operator has prepared 55 operational scenarios, of which 15 to 20 will be used for commercial operations. The passenger service charge of USD 25 per person for international departures from Long Thanh Airport has been in effect as a fee regulation since October 1, 2026 (the actual charge will only apply once flights begin). What needs to be prepared differs depending on whether you live in Ho Chi Minh City, are traveling for business over the year-end period, or are returning home in the new year. The figures are examined one by one below.

Ground staff inspecting baggage vehicles at Long Thanh International Airport as it prepares to open.
TOC

The date of December 24 is still only "scheduled"

The expression used in Vietnamese-language reporting is "dự kiến từ 24/12," which carries the wordScheduledattached to it. It has not been announced as a confirmed opening date. There was a period when English-language outlets reported a December 1 opening, based on a proposal submitted by the Civil Aviation Authority of Vietnam (CAAV). Given that the date has shifted before, it is safer to read December 24 as not yet final.

The phasing breaks down as follows. Phase 1 runs from December 2026 to March 2027, using only the west wing and central section of the passenger terminal. Phase 2 runs from April to October 2027, during which routes to Europe, Australia, South Asia, Northeast Asia, Southeast Asia, and the United States are planned. In other words, the possibility of direct flights from Japan becomes concrete from Phase 2 onward; at the time of the December 2026 opening, short-haul international routes will be the focus.

The capacity registered by Vietnam Airlines and VietJet Air is 20 to 30 flights per day, equivalent to 6 to 10% of design capacity, weighted toward domestic and short-haul international routes. Even after the new airport opens, the plan is to operate on a small scale for some time.

Initially around 30 flights per day, with a ceiling of 366 per week

Item Details
Start of commercial operations December 24, 2026 (scheduled)
Initial flight frequency Approximately 30 flights per day (20–30 on a registered basis, 6–10% of design capacity)
International routes Initially 4 routes, focused on short-haul
Maximum flights per week 366 (322 domestic, 44 international)
Airlines operating Vietnam Airlines, VietJet Air
Phase 1 December 2026 – March 2027. Terminal uses west wing and central section only
Phase 2 April – October 2027. Routes to Europe, Australia, South Asia, Northeast Asia, Southeast Asia, and the United States are planned
Operational scenarios 55 prepared. 15 to 20 will be used for commercial operations

Dividing the weekly ceiling of 366 flights by 7 gives approximately 52 flights per day, leaving headroom above the initial figure of around 30. With 44 international flights per week across 4 routes, that works out to 11 flights per route per week if distributed evenly. However, the allocation by route and operating days has not been announced, so some routes may operate daily while others operate only a few times a week. Check the days of operation when booking.

The contents of the 55 operational scenarios were not disclosed at the working meeting. All that is known is the number and the fact that 15 to 20 will be selected for commercial operations. Until the details are released, the most travelers can do on their end is work on the assumption that there will be days when things do not go as planned.

USD 25 per person for international departures; the regulation has applied since October 1

One figure already set before the airport opens is the passenger service charge. For international departures from Long Thanh Airport it is USD 25 per person, and for domestic departures it is 90,909 VND, both excluding value-added tax. The fee regulation took effect on October 1, 2026, but since the airport is not yet open, the charge will only actually appear in ticket prices once flights begin.

Airport International departure Approximate yen conversion Domestic departure
Long Thanh (Dong Nai Province) 25 US dollars Approx. ¥3,950 90,909 VND (approx. ¥550)
Tan Son Nhat (Ho Chi Minh City) USD 20 Approx. ¥3,160 Not covered in reports
Noi Bai (Hanoi) 25 US dollars Approx. ¥3,950 Not covered in reports

Yen conversions are calculated at USD 1 = approx. ¥158 and ¥1 = approx. 165 dong (both as of October 6, 2026). Long Thanh is USD 5 (approx. ¥790) more than Tan Son Nhat, putting it on par with Hanoi's Noi Bai.

That USD 5 difference has practical implications. If an international flight booked out of Tan Son Nhat is rerouted to depart from Long Thanh, the passengerpays the rate of the originally booked airport, meaning no surcharge or refund for the USD 5 difference. The same applies in the reverse direction. Because the fee is included in the airfare and passengers do not pay it at a counter, this provides a basis for avoiding confusion over the fare difference when flight changes occur at year-end.

The division of roles with Tan Son Nhat has yet to be finalized

The portion of reports that mentions Tan Son Nhat consists of a single sentence stating that both Long Thanh and Tan Son Nhat will serve as aviation gateways for the greater Ho Chi Minh City area. No specific breakdown of which routes go to which airport has been indicated.

The ratio offers a clue. The Phase 1 plan calls for 322 domestic flights and 44 international flights per day. Launching with a domestic-heavy lineup implies that some of Tan Son Nhat's domestic services will be shifted to Long Thanh. The reason for not moving international flights all at once is likely to keep volumes in check until immigration and baggage-handling operations are fully established.

It has not been decided which airport flights from Japan will use. The destinations of the initial four international routes have not been announced either, so it is also unknown at this point whether Japan routes are included. Phase 2 (April–October 2027) plans include Northeast Asia, suggesting that the handling of Japan routes will become clearer around that time, though no announcement has ruled out a transfer during Phase 1. Anyone booking flights between Japan and Ho Chi Minh City over the New Year period should be sure to check the departure and arrival airport on the booking screen. Regarding the new carrier based in Phu Quoc,no schedule for Japan routes had been announced at the time it received its first A330。

How long does it take to get from central Ho Chi Minh City to the airport, and by what means?

Long Thanh Airport is 43 kilometers from the center of District 1 (40 kilometers according to some sources). Given that Tan Son Nhat is located roughly 7 kilometers from the city center, the assumptions around getting there change considerably.

Means Estimated travel time Route / Notes
Private car / Taxi / Grab 60–90 minutes (45–60 minutes when traffic is light) Via the Ho Chi Minh City–Long Thanh–Dau Giay Expressway
Express bus 60–70 minutes (planned figure) Departing from Saigon Bus Terminal. A route with limited stops at the Ham Nghi transfer hub and Mai Chi Tho Street is planned
Tan Son Nhat Airport (for comparison) 20–40 minutes from the city center Approx. 7 km from the city center

Some road construction work will not be completed in time for the opening. The Ho Chi Minh City–Long Thanh–Dau Giay Expressway is being widened from 4 lanes to 8–10 lanes, with a target completion date of December 2026. The Long Thanh Bridge, a key element of this route, is not expected to be finished until the second quarter of 2027. This means that immediately after opening, travelers should budget their time on the assumption that they will be passing through sections that have not yet been widened.

The southern approach is handled by theBen Luc–Long Thanh Expressway. This is useful for travelers coming from the Mekong Delta direction, but it does not play a primary role for those heading from District 1 or District 3. Road conditions on the city side are also in flux, and due toa three-year one-way traffic restriction that has been imposed on the city center, the time it takes to reach the expressway entrance from the same starting point has changed compared to before.

What are officials concerned about?

  • Standing Deputy Prime Minister Pham Gia Tuc stated that ACV should resolve the difficulties faced by contractors at an early stage, and that issues involving the government would be handled on the government's side
  • While acknowledging the importance of progress, he made remarks to the effect that quality and safety are paramount, and that flights can only operate once safety is assured
  • Nguyen Duc Hung, Acting Director General of Airports Corporation of Vietnam (ACV), attended the meeting and briefed participants on the state of operational readiness
  • Vietnam Airlines and VietJet Air have registered a daily capacity of 20–30 flights, representing 6–10% of the design capacity, indicating a conservative initial operating plan

The Deputy Prime Minister's remarks framing the situation as conditional—flights only when safety is assured—are consistent with the fact that the December 24 date remains subject to change. The reason airlines have registered only 6–10% of design capacity has not been explained, but the result is that the number of flights immediately after opening will be small, leaving passengers with limited options.

What should residents and business travelers confirm before year-end?

The steps to take differ depending on one's situation. The items to prepare vary for Ho Chi Minh City residents, those traveling on business from late December into the new year, and those moving around within Vietnam.

The first thing residents should check is the departure and arrival airport for any flights already booked for December 24 or later.Long Thanh's weekly plan of 322 domestic and 44 international flights is weighted toward domestic services, but this represents the new airport's intake plan rather than the number of existing flights being transferred. Since it is up to each airline to decide which flights operate from which airport, passengers have no choice but to check their booking screens. The airport codes are LTH for Long Thanh and SGN for Tan Son Nhat. It is worth reviewing the airport code in booking confirmation emails once in mid-December. If a flight has been moved to an airport 43 kilometers away, a plan to leave home two hours before departure will need to become three hours.

Business travelers should anticipate the possibility that the outbound and return airports may differ. Flights from Japan are expected to continue arriving at Tan Son Nhat, but for those connecting to domestic flights onward to regional cities, if the connecting flight departs from Long Thanh, an inter-airport transfer will be required. Tan Son Nhat is on the northern side of the city while Long Thanh is to the east outside the city, so an inter-airport transfer involves crossing through the urban area and should be budgeted at over an hour by car. Until the means and time required for inter-airport connections are announced, it is advisable to avoid booking same-day connections.

The year-end period itself carries risks. Year-end in Vietnam is a season of increased domestic travel, and Tet (Lunar New Year) 2027 falls in February. The period from late December through January, immediately after opening, is one in which travel demand will overlap before the new airport's operations have settled. If you have plans to travel during this period, it is worth considering rail as an option alongside air. Rail refund conditions can change—the Tet train refund rate was raised to 30%—as the rules do shift.

One more thing worth revisiting is how to interpret airport fees. The international passenger service charge of USD 25 per person is included in the airfare, so there is no need to pay it on-site. However, when comparing airfare prices, flights departing from Long Thanh carry a base cost USD 5 higher than those from Tan Son Nhat. When searching for cheaper fares, if Long Thanh and Tan Son Nhat departures appear side by side on the same route, part of the price difference can be explained by this charge.

What will airlines and the travel industry need to reconfigure?

For airlines, operating costs at a newly opened airport are difficult to predict. Gate layouts, turnaround times, maintenance arrangements, and crew accommodation are all new. The fact that Vietnam Airlines and VietJet Air are starting with a conservative volume of 6–10% of design capacity is likely not unrelated to this unpredictability.

On the travel industry side, transfer logistics will need to be redesigned. A transfer from a city-center hotel to Tan Son Nhat could be scheduled in 30 minutes, but Long Thanh requires 60–90 minutes to be factored in. Package tour itineraries will need to push airport meeting times earlier, cutting into sightseeing time on the first day. Transfer costs will also rise in proportion to the distance.

In the longer term, development will advance on the Dong Nai Province side to the east of the airport. The pattern of logistics facilities and hotels being built around airports has played out in other countries as well, and the meaning of "going to the airport" as seen from central Ho Chi Minh City will change. However, this is a story for Phase 2 from 2027 onward; at the time of the late 2026 opening, it is sufficient to think of it simply as "one more distant airport has been added."

Practical information on Long Thanh International Airport

Item Details
Location Long Thanh, Dong Nai Province. 43 kilometers from District 1, Ho Chi Minh City (40 kilometers according to some sources)
Airport code IATA: LTH / ICAO: VVLT (Tan Son Nhat is SGN)
Start of commercial operations December 24, 2026 (scheduled; date subject to change)
Initial flight frequency Approx. 30 flights per day. 4 international routes
Maximum flights per week 366 (322 domestic, 44 international)
Airlines operating Vietnam Airlines, VietJet Air
International passenger service charge USD 25 per person (approx. ¥3,950, excluding VAT). The fee regulation applies from October 1, 2026. The charge becomes payable once services commence
Domestic passenger service charge 90,909 dong per person (approx. ¥550, excluding VAT)
Rate applied on rerouting The rate of the originally booked airport applies. No surcharge or refund for the USD 5 difference
Travel time from the city center 60–90 minutes by car (45–60 minutes when traffic is light). Express bus is 60–70 minutes based on planned figures
Main access roads Ho Chi Minh City–Long Thanh–Dau Giay Expressway. Widening work is underway; the Long Thanh Bridge is expected to be completed in the second quarter of 2027
Exchange-rate guide ¥1 = approx. 165 VND, USD 1 = approx. ¥158 (as of 6 October 2026)

Summary

Commercial operations at Long Thanh Airport are scheduled to begin on December 24, 2026, starting on a small scale with approximately 30 flights per day and 4 international routes. The destinations of the initial 4 international routes have not been announced, and it has not been decided which airport flights from Japan will use. The international passenger service charge of USD 25 has been in effect as a fee regulation since October 1.

If you have plans to travel in Vietnam over the year-end period, there are three things to do. In mid-December, check the airport code on any flights already booked to see whether it shows LTH or SGN. If a flight has been changed to Long Thanh, rework your transfer from the city to allow 60–90 minutes and plan to leave home three hours before departure. And avoid booking same-day connections that span Tan Son Nhat and Long Thanh until the means of inter-airport transfer are announced. As for whether the opening date remains fixed at December 24, it is worth checking ACV and the Civil Aviation Authority of Vietnam's announcements once more after December begins.

Sources

🧳 Book your Vietnam trip here
Hotel booking “agoda”
Book Vietnam hotels at great rates
Popular hotels in Da Nang, Hoi An, and Ho Chi Minh City are bookable at discounted prices. Many properties offer same-day booking and free cancellation, so you can adapt flexibly to last-minute changes of plan on the ground.
#Check the lowest price →
Advertisement (A8.net)
agoda
Overseas travel booking “NEWT”
Arrange flights and hotels together
Book your Vietnam-bound flights and accommodation all at once in the app. Earn up to 5% in points, with 24-hour Japanese-language support, so even first-time overseas travelers can prepare with peace of mind.
#Book travel the easy way →
Advertisement (A8.net)
NEWT

From flights and tours to eSIMs and travel insurance, see where to book each in the order you need them in theVietnam travel bookings summaryas well.